
A workforce of 420 men with a contractor can finish a certain piece of work in 9 months. How many extra men must be employed to complete the job in 7 months?
Answer
133.5k+ views
Hint: We start solving the problem by assigning the variables for total work that need to be done and total men required to complete the job in 7 months. We then find the total work by multiplying 420 months with 9 months. We then equate this with the multiplication of 7 months with the total people required. Once we find the total no. of people required we subtract it with 420 to get the number of extra men that need to be employed.
Complete step-by-step answer:
According to the problem, we have given that a certain piece of work can be completed in 9 months by a workforce of 420 men. We need to find the number of extra men to be employed in order to complete the job in 7 months.
Let us assume the total work to be done as x and the total men required to complete the job in 7 months be y. So, 420 men takes 9 months to complete work x.
We get the total work done by all 420 men in 9 months.
So, we get $x=420\times 9$.
$\Rightarrow x=3780$ ---(1).
Now, the amount of work obtained in equation (1) has to be completed in 7 months by y men.
So, the total amount of work done by y men in 7 months is $7\times y$ which is equal to x.
So, we get $7y=x$.
From equation (1) we get,
$\Rightarrow 7y=3780$.
$\Rightarrow y=\dfrac{3780}{7}$.
$\Rightarrow y=540$.
We have found a total of 540 men required to complete the job in 7 months. But we already have 420 men working for us. In order to find the extra men employed, we subtract 420 from the 540 people.
The extra men employed is $\left( 540-420 \right)=120$.
We have found the extra men that need to be employed in order to complete the work in 7 months as 120.
∴ The extra men that need to be employed in order to complete the work in 7 months is 120 people.
Note: We can see that there is an inverse relation between the total number of men employed and time required to complete the work done. We can also find the work done by each man in 9 months by dividing x with the total man power. Similarly, we can expect problems to find the work done by each man in a day or in a month using the obtained values.
Complete step-by-step answer:
According to the problem, we have given that a certain piece of work can be completed in 9 months by a workforce of 420 men. We need to find the number of extra men to be employed in order to complete the job in 7 months.
Let us assume the total work to be done as x and the total men required to complete the job in 7 months be y. So, 420 men takes 9 months to complete work x.
We get the total work done by all 420 men in 9 months.
So, we get $x=420\times 9$.
$\Rightarrow x=3780$ ---(1).
Now, the amount of work obtained in equation (1) has to be completed in 7 months by y men.
So, the total amount of work done by y men in 7 months is $7\times y$ which is equal to x.
So, we get $7y=x$.
From equation (1) we get,
$\Rightarrow 7y=3780$.
$\Rightarrow y=\dfrac{3780}{7}$.
$\Rightarrow y=540$.
We have found a total of 540 men required to complete the job in 7 months. But we already have 420 men working for us. In order to find the extra men employed, we subtract 420 from the 540 people.
The extra men employed is $\left( 540-420 \right)=120$.
We have found the extra men that need to be employed in order to complete the work in 7 months as 120.
∴ The extra men that need to be employed in order to complete the work in 7 months is 120 people.
Note: We can see that there is an inverse relation between the total number of men employed and time required to complete the work done. We can also find the work done by each man in 9 months by dividing x with the total man power. Similarly, we can expect problems to find the work done by each man in a day or in a month using the obtained values.
Recently Updated Pages
JEE Main 2025 Session 2 Form Correction (Closed) – What Can Be Edited

Sign up for JEE Main 2025 Live Classes - Vedantu

JEE Main Books 2023-24: Best JEE Main Books for Physics, Chemistry and Maths

JEE Main 2023 April 13 Shift 1 Question Paper with Answer Key

JEE Main 2023 April 11 Shift 2 Question Paper with Answer Key

JEE Main 2023 April 10 Shift 2 Question Paper with Answer Key

Trending doubts
JEE Main 2025 Session 2: Application Form (Out), Exam Dates (Released), Eligibility, & More

JEE Main 2025: Conversion of Galvanometer Into Ammeter And Voltmeter in Physics

An aeroplane left 50 minutes later than its schedu-class-11-maths-JEE_Main

JEE Main 2025: Derivation of Equation of Trajectory in Physics

Electric Field Due to Uniformly Charged Ring for JEE Main 2025 - Formula and Derivation

Current Loop as Magnetic Dipole and Its Derivation for JEE

Other Pages
JEE Advanced Marks vs Ranks 2025: Understanding Category-wise Qualifying Marks and Previous Year Cut-offs

NCERT Solutions for Class 11 Maths Chapter 8 Sequences and Series

NCERT Solutions for Class 11 Maths Chapter 10 Conic Sections

NCERT Solutions for Class 11 Maths Chapter 9 Straight Lines

NCERT Solutions for Class 11 Maths Chapter 12 Limits and Derivatives

NCERT Solutions for Class 11 Maths Chapter 6 Permutations and Combinations
