Answer
Verified
452.1k+ views
Hint: In this question, we need to determine the number of days in which A can complete the work alone. For this, we will use the unitary method for calculating the one-day work of A and B and then, substituting those values in work done in a day by A and B together is the summation of the work done by A alone and B alone.
Complete step-by-step answer:
Let A alone can finish the job in A days and B alone can do the same job in B days.
According to the question, A is $\left( {1\dfrac{3}{4} = \dfrac{7}{4}} \right)$ times as efficient as B, which implies that A can complete the job in less time as compared with B or B takes more time than A to complete the wok.
So, the time taken by B to complete the work alone is given by $B = \dfrac{{7A}}{4}$
Also,
A’s one day work is given as ${A_{one{\text{ day}}}} = \dfrac{1}{A}$
B’s one day work is given as ${B_{one{\text{ day}}}} = \dfrac{1}{B} = \dfrac{4}{{7A}}$
Now, A and B can complete the work working together for 7 days.
So, one day work of A and B working together is given as ${\left( {A + B} \right)_{one{\text{ day}}}} = \dfrac{1}{7}$
As the work is done in a day by A and B is the summation of the work done by A alone and B alone. So, ${\left( {A + B} \right)_{one{\text{ day}}}} = {A_{one{\text{ day}}}} + {B_{one{\text{ day}}}}$.
Now, substituting ${A_{one{\text{ day}}}} = \dfrac{1}{A}$, ${B_{one{\text{ day}}}} = \dfrac{1}{B} = \dfrac{4}{{7A}}$ and ${\left( {A + B} \right)_{one{\text{ day}}}} = \dfrac{1}{7}$ in the equation ${\left( {A + B} \right)_{one{\text{ day}}}} = {A_{one{\text{ day}}}} + {B_{one{\text{ day}}}}$ to determine the total number of days required by A to complete the work alone.
$
{\left( {A + B} \right)_{one{\text{ day}}}} = {A_{one{\text{ day}}}} + {B_{one{\text{ day}}}} \\
\dfrac{1}{7} = \dfrac{1}{A} + \dfrac{4}{{7A}} \\
\dfrac{1}{7} = \dfrac{{7 + 4}}{{7A}} \\
\dfrac{1}{7} = \dfrac{{11}}{{7A}} \\
A = 11{\text{ days}} \\
$
Hence, A can complete the work while working alone in 11 days and is $1\dfrac{3}{4}$ times as efficient as B.
So, the correct answer is “Option B”.
Note: Students must be careful while dealing with the efficiencies of the persons. If the person is more efficient then, he/she can do the work in less time than the person with lesser efficiency. Moreover, here we have converted the mixed fraction in a proper fraction by following the rule $a\dfrac{b}{c} = \dfrac{{ac + b}}{c}$.
Complete step-by-step answer:
Let A alone can finish the job in A days and B alone can do the same job in B days.
According to the question, A is $\left( {1\dfrac{3}{4} = \dfrac{7}{4}} \right)$ times as efficient as B, which implies that A can complete the job in less time as compared with B or B takes more time than A to complete the wok.
So, the time taken by B to complete the work alone is given by $B = \dfrac{{7A}}{4}$
Also,
A’s one day work is given as ${A_{one{\text{ day}}}} = \dfrac{1}{A}$
B’s one day work is given as ${B_{one{\text{ day}}}} = \dfrac{1}{B} = \dfrac{4}{{7A}}$
Now, A and B can complete the work working together for 7 days.
So, one day work of A and B working together is given as ${\left( {A + B} \right)_{one{\text{ day}}}} = \dfrac{1}{7}$
As the work is done in a day by A and B is the summation of the work done by A alone and B alone. So, ${\left( {A + B} \right)_{one{\text{ day}}}} = {A_{one{\text{ day}}}} + {B_{one{\text{ day}}}}$.
Now, substituting ${A_{one{\text{ day}}}} = \dfrac{1}{A}$, ${B_{one{\text{ day}}}} = \dfrac{1}{B} = \dfrac{4}{{7A}}$ and ${\left( {A + B} \right)_{one{\text{ day}}}} = \dfrac{1}{7}$ in the equation ${\left( {A + B} \right)_{one{\text{ day}}}} = {A_{one{\text{ day}}}} + {B_{one{\text{ day}}}}$ to determine the total number of days required by A to complete the work alone.
$
{\left( {A + B} \right)_{one{\text{ day}}}} = {A_{one{\text{ day}}}} + {B_{one{\text{ day}}}} \\
\dfrac{1}{7} = \dfrac{1}{A} + \dfrac{4}{{7A}} \\
\dfrac{1}{7} = \dfrac{{7 + 4}}{{7A}} \\
\dfrac{1}{7} = \dfrac{{11}}{{7A}} \\
A = 11{\text{ days}} \\
$
Hence, A can complete the work while working alone in 11 days and is $1\dfrac{3}{4}$ times as efficient as B.
So, the correct answer is “Option B”.
Note: Students must be careful while dealing with the efficiencies of the persons. If the person is more efficient then, he/she can do the work in less time than the person with lesser efficiency. Moreover, here we have converted the mixed fraction in a proper fraction by following the rule $a\dfrac{b}{c} = \dfrac{{ac + b}}{c}$.
Recently Updated Pages
Who among the following was the religious guru of class 7 social science CBSE
what is the correct chronological order of the following class 10 social science CBSE
Which of the following was not the actual cause for class 10 social science CBSE
Which of the following statements is not correct A class 10 social science CBSE
Which of the following leaders was not present in the class 10 social science CBSE
Garampani Sanctuary is located at A Diphu Assam B Gangtok class 10 social science CBSE
Trending doubts
A rainbow has circular shape because A The earth is class 11 physics CBSE
Which are the Top 10 Largest Countries of the World?
Fill the blanks with the suitable prepositions 1 The class 9 english CBSE
The Equation xxx + 2 is Satisfied when x is Equal to Class 10 Maths
How do you graph the function fx 4x class 9 maths CBSE
Give 10 examples for herbs , shrubs , climbers , creepers
Who gave the slogan Jai Hind ALal Bahadur Shastri BJawaharlal class 11 social science CBSE
Difference between Prokaryotic cell and Eukaryotic class 11 biology CBSE
Why is there a time difference of about 5 hours between class 10 social science CBSE