
A can do a work in 12 hours, B can do it in 14 hours. They work alternatively starting from A. A earns Rs. $15/hr.$ How much does he earn from the whole job?
Answer
412.5k+ views
Hint: To solve this question first we will calculate the total work by taking the LCM of time taken to complete the work by A and B. Then we will calculate individually the total work done by A and B. Then by multiplying the total work by A’s hourly earning we will get the desired answer.
Complete step by step answer:
We have been given that A can do a work in 12 hours, B can do in 14 hours. They work alternatively starting from A. A earns Rs. $15/hr.$
We have to find the total earning A gets from the job.
Now, let us first calculate the total work by taking the LCM of time taken to complete the work by A and B. then we will get
$\Rightarrow \text{Total work}=\text{LCM of }\left( 12,14 \right)$
Now, the LCM of 12 and 14 will be
$\begin{align}
& 2\left| \!{\underline {\,
12,14 \,}} \right. \\
& 2\left| \!{\underline {\,
6,7 \,}} \right. \\
& 3\left| \!{\underline {\,
3,7 \,}} \right. \\
& 7\left| \!{\underline {\,
1,7 \,}} \right. \\
& \text{ }\left| \!{\underline {\,
1,1 \,}} \right. \\
\end{align}$
LCM of 12 and 14 will be 84.
So the total work will be 84 units.
Now, the work done by A will be
$\begin{align}
& \Rightarrow \dfrac{84}{12} \\
& \Rightarrow 7units \\
\end{align}$
Now, the work done by B will be
$\begin{align}
& \Rightarrow \dfrac{84}{14} \\
& \Rightarrow 6 units \\
\end{align}$
Now, given in the question they work alternatively starting from A. So on the first day A completes 7 units and the next day B completes 6 units. It means in 2 days A and B complete $7+6=13units$.
Let us consider A worked 6 days and B worked 6 days so in 12 days the total work done by them will be
$\begin{align}
& \Rightarrow 13\times 6 \\
& \Rightarrow 78 units \\
\end{align}$
Now, the next day i.e. on the seventh day it’s A’s turn and he completed the remaining work i.e. $6units$ in $\dfrac{6}{7}hours$.
Now, A earns Rs. $15/hr.$ So the total amount he earns from the job will be
$\begin{align}
& \Rightarrow 12\times 15\times 3+15\times \dfrac{6}{7} \\
& \Rightarrow 540+13approx \\
& \Rightarrow 553 \\
\end{align}$
Hence A gets Rs. 553 approx from the whole job.
Note: The key concept to solve this type of question is to first calculate the total work if not given in the question. Then calculate the work done by a person in one day. Then solve further according to the demand of the question.
Complete step by step answer:
We have been given that A can do a work in 12 hours, B can do in 14 hours. They work alternatively starting from A. A earns Rs. $15/hr.$
We have to find the total earning A gets from the job.
Now, let us first calculate the total work by taking the LCM of time taken to complete the work by A and B. then we will get
$\Rightarrow \text{Total work}=\text{LCM of }\left( 12,14 \right)$
Now, the LCM of 12 and 14 will be
$\begin{align}
& 2\left| \!{\underline {\,
12,14 \,}} \right. \\
& 2\left| \!{\underline {\,
6,7 \,}} \right. \\
& 3\left| \!{\underline {\,
3,7 \,}} \right. \\
& 7\left| \!{\underline {\,
1,7 \,}} \right. \\
& \text{ }\left| \!{\underline {\,
1,1 \,}} \right. \\
\end{align}$
LCM of 12 and 14 will be 84.
So the total work will be 84 units.
Now, the work done by A will be
$\begin{align}
& \Rightarrow \dfrac{84}{12} \\
& \Rightarrow 7units \\
\end{align}$
Now, the work done by B will be
$\begin{align}
& \Rightarrow \dfrac{84}{14} \\
& \Rightarrow 6 units \\
\end{align}$
Now, given in the question they work alternatively starting from A. So on the first day A completes 7 units and the next day B completes 6 units. It means in 2 days A and B complete $7+6=13units$.
Let us consider A worked 6 days and B worked 6 days so in 12 days the total work done by them will be
$\begin{align}
& \Rightarrow 13\times 6 \\
& \Rightarrow 78 units \\
\end{align}$
Now, the next day i.e. on the seventh day it’s A’s turn and he completed the remaining work i.e. $6units$ in $\dfrac{6}{7}hours$.
Now, A earns Rs. $15/hr.$ So the total amount he earns from the job will be
$\begin{align}
& \Rightarrow 12\times 15\times 3+15\times \dfrac{6}{7} \\
& \Rightarrow 540+13approx \\
& \Rightarrow 553 \\
\end{align}$
Hence A gets Rs. 553 approx from the whole job.
Note: The key concept to solve this type of question is to first calculate the total work if not given in the question. Then calculate the work done by a person in one day. Then solve further according to the demand of the question.
Recently Updated Pages
The correct geometry and hybridization for XeF4 are class 11 chemistry CBSE

Water softening by Clarks process uses ACalcium bicarbonate class 11 chemistry CBSE

With reference to graphite and diamond which of the class 11 chemistry CBSE

A certain household has consumed 250 units of energy class 11 physics CBSE

The lightest metal known is A beryllium B lithium C class 11 chemistry CBSE

What is the formula mass of the iodine molecule class 11 chemistry CBSE

Trending doubts
When Sambhaji Maharaj died a 11 February 1689 b 11 class 8 social science CBSE

Explain the system of Dual Government class 8 social science CBSE

What is Kayal in Geography class 8 social science CBSE

Who is the author of Kadambari AKalidas B Panini C class 8 social science CBSE

In Indian rupees 1 trillion is equal to how many c class 8 maths CBSE

Advantages and disadvantages of science
