Answer
Verified
380.4k+ views
Hint: To solve this question first we will calculate the total work by taking the LCM of time taken to complete the work by A and B. Then we will calculate individually the total work done by A and B. Then by multiplying the total work by A’s hourly earning we will get the desired answer.
Complete step by step answer:
We have been given that A can do a work in 12 hours, B can do in 14 hours. They work alternatively starting from A. A earns Rs. $15/hr.$
We have to find the total earning A gets from the job.
Now, let us first calculate the total work by taking the LCM of time taken to complete the work by A and B. then we will get
$\Rightarrow \text{Total work}=\text{LCM of }\left( 12,14 \right)$
Now, the LCM of 12 and 14 will be
$\begin{align}
& 2\left| \!{\underline {\,
12,14 \,}} \right. \\
& 2\left| \!{\underline {\,
6,7 \,}} \right. \\
& 3\left| \!{\underline {\,
3,7 \,}} \right. \\
& 7\left| \!{\underline {\,
1,7 \,}} \right. \\
& \text{ }\left| \!{\underline {\,
1,1 \,}} \right. \\
\end{align}$
LCM of 12 and 14 will be 84.
So the total work will be 84 units.
Now, the work done by A will be
$\begin{align}
& \Rightarrow \dfrac{84}{12} \\
& \Rightarrow 7units \\
\end{align}$
Now, the work done by B will be
$\begin{align}
& \Rightarrow \dfrac{84}{14} \\
& \Rightarrow 6 units \\
\end{align}$
Now, given in the question they work alternatively starting from A. So on the first day A completes 7 units and the next day B completes 6 units. It means in 2 days A and B complete $7+6=13units$.
Let us consider A worked 6 days and B worked 6 days so in 12 days the total work done by them will be
$\begin{align}
& \Rightarrow 13\times 6 \\
& \Rightarrow 78 units \\
\end{align}$
Now, the next day i.e. on the seventh day it’s A’s turn and he completed the remaining work i.e. $6units$ in $\dfrac{6}{7}hours$.
Now, A earns Rs. $15/hr.$ So the total amount he earns from the job will be
$\begin{align}
& \Rightarrow 12\times 15\times 3+15\times \dfrac{6}{7} \\
& \Rightarrow 540+13approx \\
& \Rightarrow 553 \\
\end{align}$
Hence A gets Rs. 553 approx from the whole job.
Note: The key concept to solve this type of question is to first calculate the total work if not given in the question. Then calculate the work done by a person in one day. Then solve further according to the demand of the question.
Complete step by step answer:
We have been given that A can do a work in 12 hours, B can do in 14 hours. They work alternatively starting from A. A earns Rs. $15/hr.$
We have to find the total earning A gets from the job.
Now, let us first calculate the total work by taking the LCM of time taken to complete the work by A and B. then we will get
$\Rightarrow \text{Total work}=\text{LCM of }\left( 12,14 \right)$
Now, the LCM of 12 and 14 will be
$\begin{align}
& 2\left| \!{\underline {\,
12,14 \,}} \right. \\
& 2\left| \!{\underline {\,
6,7 \,}} \right. \\
& 3\left| \!{\underline {\,
3,7 \,}} \right. \\
& 7\left| \!{\underline {\,
1,7 \,}} \right. \\
& \text{ }\left| \!{\underline {\,
1,1 \,}} \right. \\
\end{align}$
LCM of 12 and 14 will be 84.
So the total work will be 84 units.
Now, the work done by A will be
$\begin{align}
& \Rightarrow \dfrac{84}{12} \\
& \Rightarrow 7units \\
\end{align}$
Now, the work done by B will be
$\begin{align}
& \Rightarrow \dfrac{84}{14} \\
& \Rightarrow 6 units \\
\end{align}$
Now, given in the question they work alternatively starting from A. So on the first day A completes 7 units and the next day B completes 6 units. It means in 2 days A and B complete $7+6=13units$.
Let us consider A worked 6 days and B worked 6 days so in 12 days the total work done by them will be
$\begin{align}
& \Rightarrow 13\times 6 \\
& \Rightarrow 78 units \\
\end{align}$
Now, the next day i.e. on the seventh day it’s A’s turn and he completed the remaining work i.e. $6units$ in $\dfrac{6}{7}hours$.
Now, A earns Rs. $15/hr.$ So the total amount he earns from the job will be
$\begin{align}
& \Rightarrow 12\times 15\times 3+15\times \dfrac{6}{7} \\
& \Rightarrow 540+13approx \\
& \Rightarrow 553 \\
\end{align}$
Hence A gets Rs. 553 approx from the whole job.
Note: The key concept to solve this type of question is to first calculate the total work if not given in the question. Then calculate the work done by a person in one day. Then solve further according to the demand of the question.
Recently Updated Pages
Who among the following was the religious guru of class 7 social science CBSE
what is the correct chronological order of the following class 10 social science CBSE
Which of the following was not the actual cause for class 10 social science CBSE
Which of the following statements is not correct A class 10 social science CBSE
Which of the following leaders was not present in the class 10 social science CBSE
Garampani Sanctuary is located at A Diphu Assam B Gangtok class 10 social science CBSE
Trending doubts
A rainbow has circular shape because A The earth is class 11 physics CBSE
Which are the Top 10 Largest Countries of the World?
Fill the blanks with the suitable prepositions 1 The class 9 english CBSE
What was the Metternich system and how did it provide class 11 social science CBSE
How do you graph the function fx 4x class 9 maths CBSE
Give 10 examples for herbs , shrubs , climbers , creepers
The Equation xxx + 2 is Satisfied when x is Equal to Class 10 Maths
What is BLO What is the full form of BLO class 8 social science CBSE
Change the following sentences into negative and interrogative class 10 english CBSE