Courses
Courses for Kids
Free study material
Offline Centres
More
Store Icon
Store
seo-qna
SearchIcon
banner

A machine P can print one lakh books in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print them in 12 hours. All the machines started at 9 a.m while machine P closed at 11 a.m. and the remaining two machines complete the work. Approximately at what time will the work be finished?
A. 11:30 a.m
B. 12 noon
C. 12:30 p.m
D. 1 p.m


Answer
VerifiedVerified
445.7k+ views
like imagedislike image
We will first start by finding the per hour printing capacity of the machines P, Q, and R respectively. Then, we will calculate their collective work for 2 hours i.e. from 9 a.m to 11 a.m, and then finally we will find the time taken to finish the work by finding the work Q and R can do collectively in 1 hour.

Complete step-by-step solution:
Now, we have been given that a machine P can print one lakh books in 8 hours, machine Q can print the same number of books in 10 hours while R can print them in 12 hours.
Now, if we take the total work that is printing 1 lakh books a 1 therefore we have,
Work done by machine P in 1 hour =18
Work done by machine Q in 1 hour =110
Work done by machine R in 1 hour =112
Now, therefore we have the work done by all the machines in 1 hour =18+110+112
=15+12+10120=37120
Now, we have been given that all the machines are started at 9 a.m and closed at 11 a.m. So, the work done by the machines in 2 hours =2×37120
=74120=3760
Now, we have been given that at 11 a.m machine P is closed and we have to find the work remaining after 11 a. m as we know that the total work is taken as 1 therefore we will subtract the work done by all the machines in 2 hours from 1 to find the remaining work left so we have,
=13760
=2360
Now, we have the work done by Q and R in 1 hour =110+112
=6+560=1160
Now, in 1160 work is done by Q and R in 1 hour. Therefore, 1 work is done by Q and R in 6011 hour, so 2360 work is done by Q and R in 6011×2360 hour
=23112Hour
So, approximately it will take 2 hours after 11 a.m for machines to complete work i.e. 1 p.m.
Hence, the correct option is (D).

Note: It is important to note that we have to find the time taken by Q and R to complete the work by the unitary method. Also, it is important to note that we have written 23112 hours approximately as given in the question.