
A takes 6 days less than the time taken by B to finish a piece of work. If both A and B together can finish it in 4 days, find the time taken by B to finish the work.
Answer
620.4k+ views
Hint:
Consider the time taken by B as ‘x’. A takes 6 days less than B, so time taken by A is (x - 6). So work done by \[B=\dfrac{1}{x}\]and \[A=\dfrac{1}{x-6}\]. Total work done by (A + B) is \[\dfrac{1}{4}\]. Solve the equation formed to get the time taken by B to finish the work.
Complete step-by-step answer:
Suppose B alone takes x days to finish the work. Then A alone can finish the work in (x - 6) days.
Now we know A’s one day work\[=\dfrac{1}{x-6}\].
B’s work per day\[=\dfrac{1}{x}\].
The total work done by A and B in one day\[=\dfrac{1}{x}+\dfrac{1}{x-6}-(1)\]
\[A+B=\dfrac{1}{x}+\dfrac{1}{x-6}\].
It’s said that A and B can finish a work together in 4 days.
\[\therefore A+B=\dfrac{1}{4}-(2)\]
Now, Equating equation (1) and equation (2),
\[\dfrac{1}{x}+\dfrac{1}{x-6}=\dfrac{1}{4}\]
Simplifying the LHS, \[\dfrac{\left( x-6 \right)+x}{x\left( x-6 \right)}=\dfrac{1}{4}\]
\[\Rightarrow \dfrac{2x-6}{x\left( x-6 \right)}=\dfrac{1}{4}\]
Now cross multiplying them, then the equation becomes,
\[4\left( 2x-6 \right)=x\left( x-6 \right)\]
Opening the brackets and simplifying them,
\[\begin{align}
& 8x-24={{x}^{2}}-6x \\
& \Rightarrow {{x}^{2}}-6x-8x+24=0 \\
& {{x}^{2}}-x\left( 6+8 \right)+24=0 \\
& {{x}^{2}}-14x+24=0-(3) \\
\end{align}\]
Equation (3) is similar to the general quadratic equation, \[a{{x}^{2}}+bx+c=0\].
Comparing both general equation and equation (3), we get the values of constants a = 1, b = -14, c = 24.
Now, applying the above value in the quadratic formula,
\[\begin{align}
& \dfrac{-b\pm \sqrt{{{b}^{2}}-4ac}}{2a}=\dfrac{-\left( -14 \right)\pm \sqrt{{{\left( -14 \right)}^{2}}-4\times 1\times 24}}{2\times 1} \\
& =\dfrac{14\pm \sqrt{196-96}}{2}=\dfrac{14\pm \sqrt{100}}{2}=\dfrac{14\pm 10}{2} \\
\end{align}\]
The roots are \[\left( \dfrac{14+10}{2} \right)\]and \[\left( \dfrac{14-10}{2} \right)\]= 12 and 2.
The value of x cannot be less than 6.
If B takes the time of 2 days, then the time taken by A becomes, \[x-6=2-6=-4\]days.
i.e. time taken cannot be negative.
\[\therefore x=12\].
i.e. It would take B a period of 12 days to finish the job.
Note:
If we were asked to find the time taken by A to finish the work alone then we got x=12 i.e. the time taken by B alone to do a work. So, time taken by A is 12 – 6 = 6 days. As A takes 6 days less than the time taken by B. If we are adding time taken by (A + B) together\[=\dfrac{1}{6}+\dfrac{1}{12}=\dfrac{12+6}{12\times 6}=\dfrac{1}{4}\].
Consider the time taken by B as ‘x’. A takes 6 days less than B, so time taken by A is (x - 6). So work done by \[B=\dfrac{1}{x}\]and \[A=\dfrac{1}{x-6}\]. Total work done by (A + B) is \[\dfrac{1}{4}\]. Solve the equation formed to get the time taken by B to finish the work.
Complete step-by-step answer:
Suppose B alone takes x days to finish the work. Then A alone can finish the work in (x - 6) days.
Now we know A’s one day work\[=\dfrac{1}{x-6}\].
B’s work per day\[=\dfrac{1}{x}\].
The total work done by A and B in one day\[=\dfrac{1}{x}+\dfrac{1}{x-6}-(1)\]
\[A+B=\dfrac{1}{x}+\dfrac{1}{x-6}\].
It’s said that A and B can finish a work together in 4 days.
\[\therefore A+B=\dfrac{1}{4}-(2)\]
Now, Equating equation (1) and equation (2),
\[\dfrac{1}{x}+\dfrac{1}{x-6}=\dfrac{1}{4}\]
Simplifying the LHS, \[\dfrac{\left( x-6 \right)+x}{x\left( x-6 \right)}=\dfrac{1}{4}\]
\[\Rightarrow \dfrac{2x-6}{x\left( x-6 \right)}=\dfrac{1}{4}\]
Now cross multiplying them, then the equation becomes,
\[4\left( 2x-6 \right)=x\left( x-6 \right)\]
Opening the brackets and simplifying them,
\[\begin{align}
& 8x-24={{x}^{2}}-6x \\
& \Rightarrow {{x}^{2}}-6x-8x+24=0 \\
& {{x}^{2}}-x\left( 6+8 \right)+24=0 \\
& {{x}^{2}}-14x+24=0-(3) \\
\end{align}\]
Equation (3) is similar to the general quadratic equation, \[a{{x}^{2}}+bx+c=0\].
Comparing both general equation and equation (3), we get the values of constants a = 1, b = -14, c = 24.
Now, applying the above value in the quadratic formula,
\[\begin{align}
& \dfrac{-b\pm \sqrt{{{b}^{2}}-4ac}}{2a}=\dfrac{-\left( -14 \right)\pm \sqrt{{{\left( -14 \right)}^{2}}-4\times 1\times 24}}{2\times 1} \\
& =\dfrac{14\pm \sqrt{196-96}}{2}=\dfrac{14\pm \sqrt{100}}{2}=\dfrac{14\pm 10}{2} \\
\end{align}\]
The roots are \[\left( \dfrac{14+10}{2} \right)\]and \[\left( \dfrac{14-10}{2} \right)\]= 12 and 2.
The value of x cannot be less than 6.
If B takes the time of 2 days, then the time taken by A becomes, \[x-6=2-6=-4\]days.
i.e. time taken cannot be negative.
\[\therefore x=12\].
i.e. It would take B a period of 12 days to finish the job.
Note:
If we were asked to find the time taken by A to finish the work alone then we got x=12 i.e. the time taken by B alone to do a work. So, time taken by A is 12 – 6 = 6 days. As A takes 6 days less than the time taken by B. If we are adding time taken by (A + B) together\[=\dfrac{1}{6}+\dfrac{1}{12}=\dfrac{12+6}{12\times 6}=\dfrac{1}{4}\].
Recently Updated Pages
Master Class 10 Computer Science: Engaging Questions & Answers for Success

Master Class 10 General Knowledge: Engaging Questions & Answers for Success

Master Class 10 English: Engaging Questions & Answers for Success

Master Class 10 Social Science: Engaging Questions & Answers for Success

Master Class 10 Maths: Engaging Questions & Answers for Success

Master Class 10 Science: Engaging Questions & Answers for Success

Trending doubts
What is the median of the first 10 natural numbers class 10 maths CBSE

Which women's tennis player has 24 Grand Slam singles titles?

Who is the Brand Ambassador of Incredible India?

Why is there a time difference of about 5 hours between class 10 social science CBSE

Write a letter to the principal requesting him to grant class 10 english CBSE

State and prove converse of BPT Basic Proportionality class 10 maths CBSE

