Choose the correct answer from the alternatives given.
15 men can complete a work in 10 days while 20 boys can complete the same work in 15 days. How many days will 10 men and 10 boys take to complete the remaining work?
(a). 10
(b). 8
(c).12
(d). 9
Answer
Verified
509.4k+ views
Hint:– Break down each phrase of the question to understand it better. Then find out the rate at which the work is completed with respect to boys, men. Also, find out the amount of work that can be done in one day by men and boys. Change it into one parameter to get the answer.
Complete step-by-step solution -
Given Data – 15 men can do the work in 10 days
∴One day work is completed by 15 × 10 men = 150 men.
Also, 20 boys can complete the work in 15 days
∴In one day the work is completed by 20 × 15 = 300 boys.
∴Work of 150 men = Work of 300 boys
⟹Work of one man = = Work of 2 boys
⟹Work of 10 men = 2 × 10 = Work of 20 boys
We should find out work done by 10 men and 10 boys = 10(2) + 10 = 30 boys
Also given, 20 boys do the work in 15 days
⟹30 boys can do it in =10 days.
Hence, Option A is the correct answer.
Note:–The key to solving this type of question is to understand exactly what was given and make relations accordingly. Then we find out the rate at which the work can be done with respect to each parameter. Then build a relation for the two parameters and convert everything into a single parameter to determine the answer.
Complete step-by-step solution -
Given Data – 15 men can do the work in 10 days
∴One day work is completed by 15 × 10 men = 150 men.
Also, 20 boys can complete the work in 15 days
∴In one day the work is completed by 20 × 15 = 300 boys.
∴Work of 150 men = Work of 300 boys
⟹Work of one man = = Work of 2 boys
⟹Work of 10 men = 2 × 10 = Work of 20 boys
We should find out work done by 10 men and 10 boys = 10(2) + 10 = 30 boys
Also given, 20 boys do the work in 15 days
⟹30 boys can do it in =10 days.
Hence, Option A is the correct answer.
Note:–The key to solving this type of question is to understand exactly what was given and make relations accordingly. Then we find out the rate at which the work can be done with respect to each parameter. Then build a relation for the two parameters and convert everything into a single parameter to determine the answer.
Recently Updated Pages
What percentage of the area in India is covered by class 10 social science CBSE
The area of a 6m wide road outside a garden in all class 10 maths CBSE
What is the electric flux through a cube of side 1 class 10 physics CBSE
If one root of x2 x k 0 maybe the square of the other class 10 maths CBSE
The radius and height of a cylinder are in the ratio class 10 maths CBSE
An almirah is sold for 5400 Rs after allowing a discount class 10 maths CBSE
Trending doubts
The Equation xxx + 2 is Satisfied when x is Equal to Class 10 Maths
Why is there a time difference of about 5 hours between class 10 social science CBSE
Change the following sentences into negative and interrogative class 10 english CBSE
Write a letter to the principal requesting him to grant class 10 english CBSE
Explain the Treaty of Vienna of 1815 class 10 social science CBSE
Write an application to the principal requesting five class 10 english CBSE