Given, A, B, and C can reap a field in $15\dfrac{3}{4}$ days, B, C, and D in 14 days, C, D, and A in 18 days, and D, A, and B in 21 days. In what time A, B, C, and D together reap it?
Answer
Verified
421.2k+ views
Hint: To solve this question we consider that the total amount of work is 100%. Then, we will find the percentage of work done by A, B, and C in one day, the percentage of work done by B, C, and D in one day, the percentage of work done by C, D, and A in one day, and the percentage of work done by D, A and B in one day. Then, with this information, we will find the percentage of work done in one day when A works alone and then find the number of days required to complete the work.
Complete step by step answer:
Given: - A, B, and C can reap a field in $15\dfrac{3}{4}$ days.
B, C, and D can reap a field in 14 days,
C, D, and A can reap a field in 18 days.
D, A, and B can reap a field in 21 days.
A, B, and C require $15\dfrac{3}{4}$ days to complete 100 % work. So, the percentage of work completed by A, B, and C in one day can found out as:
$ \Rightarrow A + B + C = \dfrac{{100\% }}{{\dfrac{{63}}{4}}}$
Cancel out the common factor,
$ \Rightarrow A + B + C = 6.35\% $ ….. (1)
B, C, and D required 14 days to complete 100 % work. So, the percentage of work completed by B, C, and D in one day can found out as:
$ \Rightarrow B + C + D = \dfrac{{100\% }}{{14}}$
Cancel out the common factor,
$ \Rightarrow B + C + D = 7.14\% $ ….. (2)
C, D, and A required 18 days to complete 100 % work. So, the percentage of work completed by C, D, and A in one day can found out as:
$ \Rightarrow C + D + A = \dfrac{{100\% }}{{18}}$
Cancel out the common factor,
$ \Rightarrow C + D + A = 5.55\% $ ….. (3)
D, A, and B required 21 days to complete 100 % work. So, the percentage of work completed by D, A, and B in one day can found out as:
$ \Rightarrow D + A + B = \dfrac{{100\% }}{{21}}$
Cancel out the common factor,
$ \Rightarrow D + A + B = 4.76\% $ ….. (4)
Now add equation (1), (2), (3), and (4) and find the value of A + B + C + D.
$ \Rightarrow 3A + 3B + 3C = 6.35\% + 7.14\% + 5.55\% + 4.76\% $
Add the terms on the right side,
$ \Rightarrow 3\left( {A + B + C + D} \right) = 23.8\% $
Divide both sides by 3,
$ \Rightarrow A + B + C + D = 7.93\% $
So, 7.93% of work is completed in one day if A, B, C, and D work together.
Therefore, the number of days to complete the work is,
$\therefore \dfrac{{100}}{{7.93}} = 12.6 = 12\dfrac{3}{5}$
Hence, the number of days to complete the work is $12\dfrac{3}{5}$ days.
Note:
This question can be solved in another way.
Step by step answer: -
Given: - A, B, and C can reap a field in $15\dfrac{3}{4}$ days.
B, C, and D can reap a field in 14 days,
C, D, and A can reap a field in 18 days.
D, A, and B can reap a field in 21 days.
A, B, and C require $15\dfrac{3}{4}$ days to complete the work. So, the work completed by A, B, and C in one day can found out as:
$ \Rightarrow \dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C} = \dfrac{1}{{\dfrac{{63}}{4}}}$
Multiply 4 in the numerator,
$ \Rightarrow \dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C} = \dfrac{4}{{63}}$ ….. (1)
B, C, and D required 14 days to complete the work. So, the work completed by B, C, and D in one day can found out as:
$ \Rightarrow \dfrac{1}{B} + \dfrac{1}{C} + \dfrac{1}{D} = \dfrac{1}{{14}}$ ….. (2)
C, D, and A required 18 days to complete the work. So, the work completed by C, D, and A in one day can found out as:
$ \Rightarrow \dfrac{1}{C} + \dfrac{1}{D} + \dfrac{1}{A} = \dfrac{1}{{18}}$ ….. (3)
D, A, and B required 21 days to complete the work. So, the work completed by D, A, and B in one day can found out as:
$ \Rightarrow \dfrac{1}{D} + \dfrac{1}{A} + \dfrac{1}{B} = \dfrac{1}{{21}}$ ….. (4)
Now add equation (1), (2), (3), and (4) and find the value of A + B + C + D.
$\dfrac{3}{A} + \dfrac{3}{B} + \dfrac{3}{C} + \dfrac{3}{D} = \dfrac{4}{{63}} + \dfrac{1}{{14}} + \dfrac{1}{{18}} + \dfrac{1}{{21}}$
Take LCM on the right side,
$ \Rightarrow 3\left( {\dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C} + \dfrac{1}{D}} \right) = \dfrac{{8 + 9 + 7 + 6}}{{126}}$
Add the terms on the right side,
$ \Rightarrow 3\left( {\dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C} + \dfrac{1}{D}} \right) = \dfrac{{30}}{{126}}$
Cancel out the common factors,
$ \Rightarrow 3\left( {\dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C} + \dfrac{1}{D}} \right) = \dfrac{5}{{21}}$
Divide both sides by 3,
$ \Rightarrow \dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C} + \dfrac{1}{D} = \dfrac{5}{{63}}$
So, $\dfrac{5}{{63}}$ of work is completed in one day if A, B, C, and D work together.
Therefore, the number of days to complete the work is,
$\therefore \dfrac{1}{{\dfrac{5}{{63}}}} = \dfrac{{63}}{5} = 12\dfrac{3}{5}$
Hence, the number of days to complete the work is $12\dfrac{3}{5}$ days.
Complete step by step answer:
Given: - A, B, and C can reap a field in $15\dfrac{3}{4}$ days.
B, C, and D can reap a field in 14 days,
C, D, and A can reap a field in 18 days.
D, A, and B can reap a field in 21 days.
A, B, and C require $15\dfrac{3}{4}$ days to complete 100 % work. So, the percentage of work completed by A, B, and C in one day can found out as:
$ \Rightarrow A + B + C = \dfrac{{100\% }}{{\dfrac{{63}}{4}}}$
Cancel out the common factor,
$ \Rightarrow A + B + C = 6.35\% $ ….. (1)
B, C, and D required 14 days to complete 100 % work. So, the percentage of work completed by B, C, and D in one day can found out as:
$ \Rightarrow B + C + D = \dfrac{{100\% }}{{14}}$
Cancel out the common factor,
$ \Rightarrow B + C + D = 7.14\% $ ….. (2)
C, D, and A required 18 days to complete 100 % work. So, the percentage of work completed by C, D, and A in one day can found out as:
$ \Rightarrow C + D + A = \dfrac{{100\% }}{{18}}$
Cancel out the common factor,
$ \Rightarrow C + D + A = 5.55\% $ ….. (3)
D, A, and B required 21 days to complete 100 % work. So, the percentage of work completed by D, A, and B in one day can found out as:
$ \Rightarrow D + A + B = \dfrac{{100\% }}{{21}}$
Cancel out the common factor,
$ \Rightarrow D + A + B = 4.76\% $ ….. (4)
Now add equation (1), (2), (3), and (4) and find the value of A + B + C + D.
$ \Rightarrow 3A + 3B + 3C = 6.35\% + 7.14\% + 5.55\% + 4.76\% $
Add the terms on the right side,
$ \Rightarrow 3\left( {A + B + C + D} \right) = 23.8\% $
Divide both sides by 3,
$ \Rightarrow A + B + C + D = 7.93\% $
So, 7.93% of work is completed in one day if A, B, C, and D work together.
Therefore, the number of days to complete the work is,
$\therefore \dfrac{{100}}{{7.93}} = 12.6 = 12\dfrac{3}{5}$
Hence, the number of days to complete the work is $12\dfrac{3}{5}$ days.
Note:
This question can be solved in another way.
Step by step answer: -
Given: - A, B, and C can reap a field in $15\dfrac{3}{4}$ days.
B, C, and D can reap a field in 14 days,
C, D, and A can reap a field in 18 days.
D, A, and B can reap a field in 21 days.
A, B, and C require $15\dfrac{3}{4}$ days to complete the work. So, the work completed by A, B, and C in one day can found out as:
$ \Rightarrow \dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C} = \dfrac{1}{{\dfrac{{63}}{4}}}$
Multiply 4 in the numerator,
$ \Rightarrow \dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C} = \dfrac{4}{{63}}$ ….. (1)
B, C, and D required 14 days to complete the work. So, the work completed by B, C, and D in one day can found out as:
$ \Rightarrow \dfrac{1}{B} + \dfrac{1}{C} + \dfrac{1}{D} = \dfrac{1}{{14}}$ ….. (2)
C, D, and A required 18 days to complete the work. So, the work completed by C, D, and A in one day can found out as:
$ \Rightarrow \dfrac{1}{C} + \dfrac{1}{D} + \dfrac{1}{A} = \dfrac{1}{{18}}$ ….. (3)
D, A, and B required 21 days to complete the work. So, the work completed by D, A, and B in one day can found out as:
$ \Rightarrow \dfrac{1}{D} + \dfrac{1}{A} + \dfrac{1}{B} = \dfrac{1}{{21}}$ ….. (4)
Now add equation (1), (2), (3), and (4) and find the value of A + B + C + D.
$\dfrac{3}{A} + \dfrac{3}{B} + \dfrac{3}{C} + \dfrac{3}{D} = \dfrac{4}{{63}} + \dfrac{1}{{14}} + \dfrac{1}{{18}} + \dfrac{1}{{21}}$
Take LCM on the right side,
$ \Rightarrow 3\left( {\dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C} + \dfrac{1}{D}} \right) = \dfrac{{8 + 9 + 7 + 6}}{{126}}$
Add the terms on the right side,
$ \Rightarrow 3\left( {\dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C} + \dfrac{1}{D}} \right) = \dfrac{{30}}{{126}}$
Cancel out the common factors,
$ \Rightarrow 3\left( {\dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C} + \dfrac{1}{D}} \right) = \dfrac{5}{{21}}$
Divide both sides by 3,
$ \Rightarrow \dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C} + \dfrac{1}{D} = \dfrac{5}{{63}}$
So, $\dfrac{5}{{63}}$ of work is completed in one day if A, B, C, and D work together.
Therefore, the number of days to complete the work is,
$\therefore \dfrac{1}{{\dfrac{5}{{63}}}} = \dfrac{{63}}{5} = 12\dfrac{3}{5}$
Hence, the number of days to complete the work is $12\dfrac{3}{5}$ days.
Recently Updated Pages
10 Examples of Evaporation in Daily Life with Explanations
10 Examples of Diffusion in Everyday Life
1 g of dry green algae absorb 47 times 10 3 moles of class 11 chemistry CBSE
If x be real then the maximum value of 5 + 4x 4x2 will class 10 maths JEE_Main
If the coordinates of the points A B and C be 443 23 class 10 maths JEE_Main
What happens when dilute hydrochloric acid is added class 10 chemistry JEE_Main
Trending doubts
Fill the blanks with the suitable prepositions 1 The class 9 english CBSE
Which are the Top 10 Largest Countries of the World?
How do you graph the function fx 4x class 9 maths CBSE
Who was the leader of the Bolshevik Party A Leon Trotsky class 9 social science CBSE
The Equation xxx + 2 is Satisfied when x is Equal to Class 10 Maths
Differentiate between homogeneous and heterogeneous class 12 chemistry CBSE
Difference between Prokaryotic cell and Eukaryotic class 11 biology CBSE
Which is the largest saltwater lake in India A Chilika class 8 social science CBSE
Ghatikas during the period of Satavahanas were aHospitals class 6 social science CBSE