
If A and B can do a piece of work in 6 days and A alone can do it in 9 days. Then what is the time taken by B alone to do the work?
(a) 18 days
(b) 15 days
(c) 12 days
(d) $ 7\dfrac{1}{2} $ days
Answer
493.5k+ views
Hint: First try to find the fraction of work done by both A and B in one day and then find the fraction of work done by A alone in a day after that find the fraction of work done by B alone in one day. Using the information i.e. fraction of work done by B alone in a day, we can easily find out the amount of time B will take to finish the work alone.
Complete step-by-step answer:
It is given that A and B can do a piece of work in 6 days. Let us suppose the amount of work as X.
If A and B both can finish X amount work in 6 days then, we get that the work done in one day is $ \dfrac{1}{6}th $ of the total amount of work, i.e.
Work done in one day by both A and B = $ \dfrac{X}{6} $
It is also given that A finishes the work in 9 days, hence we get that if A finishes work in 9 days then work done by A in 1 day is $ \dfrac{1}{9}th $ of the total work, so we get
Work done by A alone in 1 day = $ \dfrac{X}{9} $
Now, we know that work done by B alone in one day would be equal to
= (work done by both in 1 day) – (work done by A alone in 1 day)
= $ \dfrac{X}{6} $ - $ \dfrac{X}{9} $
By taking LCM we get,
= $ \dfrac{9X-6X}{9\times 6} $
= $ \dfrac{3X}{54} $
= $ \dfrac{X}{18} $
So, work done by B alone in 1 day is = $ \dfrac{1}{18}th $ of the total amount of work.
Multiplying by 18 on both sides of above expression we get,
Work done by B alone in 18 days = total amount of work
Hence B alone can do the work in 18 days
So, the correct answer is “Option A”.
Note: Be careful while solving this question and don’t try to use any shortcuts here as it can lead to wrong answers.
This question can also be solved by considering amount of work directly for 6 days instead of 1,
For example,
X amount of work is done by both A and B in 6 days,
And $ \dfrac{X}{9} $ amount of work is done by A alone in one day
So, $ \dfrac{6X}{9} $ is the amount of work done by A alone in 6 days
Amount of work done by B in 6 days = work done by both in 6 days – work done by A alone in 6 days
= $ X-\dfrac{6X}{9} $
$ \begin{align}
& =\dfrac{9X-6X}{9} \\
& =\dfrac{3X}{9} \\
& =\dfrac{X}{3} \\
\end{align} $
Hence amount of work done by B alone in 6 days is $ \dfrac{1}{3}rd $ of total work,
So, total work done will be done by B alone in (6 $ \times $ 3) days i.e. 18 days.
Complete step-by-step answer:
It is given that A and B can do a piece of work in 6 days. Let us suppose the amount of work as X.
If A and B both can finish X amount work in 6 days then, we get that the work done in one day is $ \dfrac{1}{6}th $ of the total amount of work, i.e.
Work done in one day by both A and B = $ \dfrac{X}{6} $
It is also given that A finishes the work in 9 days, hence we get that if A finishes work in 9 days then work done by A in 1 day is $ \dfrac{1}{9}th $ of the total work, so we get
Work done by A alone in 1 day = $ \dfrac{X}{9} $
Now, we know that work done by B alone in one day would be equal to
= (work done by both in 1 day) – (work done by A alone in 1 day)
= $ \dfrac{X}{6} $ - $ \dfrac{X}{9} $
By taking LCM we get,
= $ \dfrac{9X-6X}{9\times 6} $
= $ \dfrac{3X}{54} $
= $ \dfrac{X}{18} $
So, work done by B alone in 1 day is = $ \dfrac{1}{18}th $ of the total amount of work.
Multiplying by 18 on both sides of above expression we get,
Work done by B alone in 18 days = total amount of work
Hence B alone can do the work in 18 days
So, the correct answer is “Option A”.
Note: Be careful while solving this question and don’t try to use any shortcuts here as it can lead to wrong answers.
This question can also be solved by considering amount of work directly for 6 days instead of 1,
For example,
X amount of work is done by both A and B in 6 days,
And $ \dfrac{X}{9} $ amount of work is done by A alone in one day
So, $ \dfrac{6X}{9} $ is the amount of work done by A alone in 6 days
Amount of work done by B in 6 days = work done by both in 6 days – work done by A alone in 6 days
= $ X-\dfrac{6X}{9} $
$ \begin{align}
& =\dfrac{9X-6X}{9} \\
& =\dfrac{3X}{9} \\
& =\dfrac{X}{3} \\
\end{align} $
Hence amount of work done by B alone in 6 days is $ \dfrac{1}{3}rd $ of total work,
So, total work done will be done by B alone in (6 $ \times $ 3) days i.e. 18 days.
Recently Updated Pages
The correct geometry and hybridization for XeF4 are class 11 chemistry CBSE

Water softening by Clarks process uses ACalcium bicarbonate class 11 chemistry CBSE

With reference to graphite and diamond which of the class 11 chemistry CBSE

A certain household has consumed 250 units of energy class 11 physics CBSE

The lightest metal known is A beryllium B lithium C class 11 chemistry CBSE

What is the formula mass of the iodine molecule class 11 chemistry CBSE

Trending doubts
On which river Salal project is situated A River Sutlej class 8 social science CBSE

When Sambhaji Maharaj died a 11 February 1689 b 11 class 8 social science CBSE

Explain the system of Dual Government class 8 social science CBSE

What is Kayal in Geography class 8 social science CBSE

In Indian rupees 1 trillion is equal to how many c class 8 maths CBSE

Sketch larynx and explain its function in your own class 8 physics CBSE
