Courses
Courses for Kids
Free study material
Offline Centres
More
Store Icon
Store

If $m$ men can do a job in $p$ days, then $(m + r)$ men can do the job in how many days?
(A)$(p + r)$days
(B) $\dfrac{{mp}}{{m + r}}$days
(C) $\dfrac{p}{{m + r}}$days
(D) $\dfrac{{m + r}}{p}$days

seo-qna
SearchIcon
Answer
VerifiedVerified
469.8k+ views
Hint: To solve this question in detail one should have a deep knowledge of the Unitary method. In this whole solution, we will apply the unitary method many times.

Complete step by step answer:
By applying unitary method we can get,
 Work done by $m$men in $p$ days$ = 1$ Statement (1)
$\therefore $ Work done by $m$men in $1$ day$ = \dfrac{1}{p}$part Statement (2)
And Work done by $1$man in $1$ day$ = \dfrac{1}{{mp}}$part Statement (3)
Now, we have to find the number of days required to complete the job by $(m + r)$men,
Therefore after statement (3) we can write that,
Work done by $(m + r)$men in $1$ day$ = \dfrac{{(m + r)}}{{mp}}$ part
Now again by applying the unitary method in a different way to find the time taken by $(m + r)$men to do the job,
 Time taken by $(m + r)$men to do $\dfrac{{(m + r)}}{{mp}}$part of work$ = 1$ day
$\therefore $ Time taken by $(m + r)$men to do full work (it means$1$)$ = \dfrac{{1 \times 1}}{{(\dfrac{{m + r}}{{mp}})}} = \dfrac{{mp}}{{m + r}}$ days.
Hence $(m + r)$ men can do the job in $\dfrac{{mp}}{{m + r}}$days.
Answer- (B)

Note:
Second method-
There is also a formula based method to solve this question,
If ${M_1}$men can do ${W_1}$ work in ${D_1}$ days working ${H_1}$hours per day and ${M_2}$men can do ${W_2}$ work in ${D_2}$ days working ${H_2}$hours per day, then
\[\dfrac{{{M_1}{D_1}{H_1}}}{{{W_1}}} = \dfrac{{{M_2}{D_2}{H_2}}}{{{W_2}}}\]
If you do not have one of these values then put $1$in place of that.