
A can do a piece of work in 80 days. He works at it for 10 days and then B alone finishes remaining work in 42 days. In how many days could both do it?
Answer
533.1k+ views
Hint: Divide the works in parts and find out how many parts of work A and B do alone in 1 day. Assume that both can do the work in days. Find out how many parts of the work A will do and how many B will do in these days. Take their sum and equate it with 80.
Complete step-by-step answer:
Let A do 1 part of work each day. Therefore, in 80 days he will do 80% of the work. Hence, the work contains 80 parts. If he works for 10 days then he will complete only 10 part of the work and therefore the remaining 70 part of the work will be done by B. It is given that B does this work in 42 days. Therefore, in one day B does, part of the work.
Let us assume that both will complete the work in days. Therefore, in days A will do part of the work and B will do part of the work. The sum of their parts will be equal to the total part of the work, that is 80. Therefore,
Hence, both will complete the work in 30 days.
Note: We have divided the work in parts to make it free from assumption of 2 variables. Further we have used a unitary method to calculate the part of work that B does in one day. The sum of their individual contribution to the work will be equal to the total work.
Complete step-by-step answer:
Let A do 1 part of work each day. Therefore, in 80 days he will do 80% of the work. Hence, the work contains 80 parts. If he works for 10 days then he will complete only 10 part of the work and therefore the remaining 70 part of the work will be done by B. It is given that B does this work in 42 days. Therefore, in one day B does,
Let us assume that both will complete the work in
Hence, both will complete the work in 30 days.
Note: We have divided the work in parts to make it free from assumption of 2 variables. Further we have used a unitary method to calculate the part of work that B does in one day. The sum of their individual contribution to the work will be equal to the total work.
Recently Updated Pages
Master Class 11 Economics: Engaging Questions & Answers for Success

Master Class 11 Business Studies: Engaging Questions & Answers for Success

Master Class 11 Accountancy: Engaging Questions & Answers for Success

Questions & Answers - Ask your doubts

Master Class 11 Accountancy: Engaging Questions & Answers for Success

Master Class 11 Science: Engaging Questions & Answers for Success

Trending doubts
Full Form of IASDMIPSIFSIRSPOLICE class 7 social science CBSE

Whom did king Ashoka send to Sri Lanka to spread Buddhism class 7 social science CBSE

The southernmost point of the Indian mainland is known class 7 social studies CBSE

How many crores make 10 million class 7 maths CBSE

AIM To prepare stained temporary mount of onion peel class 7 biology CBSE

Find HCF and LCM of 120 and 144 by using Fundamental class 7 maths CBSE
