Answer
Verified
500.4k+ views
Hint – The number of days on which the work can be completed by A and B separately is given to us. Now A and B have worked together for 4 days and we need to find the fraction of work which is left. SO let the total work to be done by A and B be P. Using the unitary methods calculate the work done by A and B by per day and using this calculate the work done by them together in 4 days.
“Complete step-by-step answer:”
It is given that A can do a work in 15 days and B can do a work in 20 days.
If A and B have done work for 4 days together then we have to find out the fraction of work left.
Let the total work be P.
So, the work done by A per day is the ratio of total work divided by the number of days in which A can do the work.
So, the work done by A per day $ = \dfrac{P}{{15}}$.
Similarly, the work done by B per day $ = \dfrac{P}{{20}}$.
Now the work done by A and B in four days is
$ \Rightarrow \left( {\dfrac{P}{{15}} + \dfrac{P}{{20}}} \right) \times 4$
Now simplify this we have
$ \Rightarrow \left( {\dfrac{P}{{15}} + \dfrac{P}{{20}}} \right) \times 4 = \dfrac{{28}}{{60}}P$
So, the work left is total work minus the work done by A and B in four days.
So, work left $ = P - \dfrac{{28}}{{60}}P = \dfrac{{32}}{{60}}P = \dfrac{8}{{15}}P$
So, the fraction of work left is $\dfrac{8}{{15}}$.
So, this is the required answer.
Note – Whenever we face such types of problems the key concept here is to simply apply a unitary method to calculate the work done by the individuals per day then use the conditions and information given in the question to get the required entity.
“Complete step-by-step answer:”
It is given that A can do a work in 15 days and B can do a work in 20 days.
If A and B have done work for 4 days together then we have to find out the fraction of work left.
Let the total work be P.
So, the work done by A per day is the ratio of total work divided by the number of days in which A can do the work.
So, the work done by A per day $ = \dfrac{P}{{15}}$.
Similarly, the work done by B per day $ = \dfrac{P}{{20}}$.
Now the work done by A and B in four days is
$ \Rightarrow \left( {\dfrac{P}{{15}} + \dfrac{P}{{20}}} \right) \times 4$
Now simplify this we have
$ \Rightarrow \left( {\dfrac{P}{{15}} + \dfrac{P}{{20}}} \right) \times 4 = \dfrac{{28}}{{60}}P$
So, the work left is total work minus the work done by A and B in four days.
So, work left $ = P - \dfrac{{28}}{{60}}P = \dfrac{{32}}{{60}}P = \dfrac{8}{{15}}P$
So, the fraction of work left is $\dfrac{8}{{15}}$.
So, this is the required answer.
Note – Whenever we face such types of problems the key concept here is to simply apply a unitary method to calculate the work done by the individuals per day then use the conditions and information given in the question to get the required entity.
Recently Updated Pages
A particle executes simple harmonic motion with a frequency class 11 physics JEE_Main
What happens to the gravitational force between two class 11 physics NEET
Let x y be the real number satisfying the equation class 11 maths JEE_Main
The locus of the centre of the circles which cut the class 11 maths JEE_Main
A wire of length L and radius r is clamped rigidly class 11 physics JEE_Main
To break a wire a stress of 2106 Nm2 is required If class 11 physics JEE_Main
Trending doubts
Which is the longest day and shortest night in the class 11 sst CBSE
Why is steel more elastic than rubber class 11 physics CBSE
Difference between Prokaryotic cell and Eukaryotic class 11 biology CBSE
Define the term system surroundings open system closed class 11 chemistry CBSE
In a democracy the final decisionmaking power rests class 11 social science CBSE
In the tincture of iodine which is solute and solv class 11 chemistry CBSE