Answer
Verified
468.6k+ views
Hint: In this particular question use the concept that if 12 men can do a work in 12 days so the 1 day work of 12 men is $\dfrac{1}{{12}}$, therefore one day work of 1 man is $\dfrac{1}{{12 \times 12}}$,so the 6 day work of 12 men is $\dfrac{{6 \times 12}}{{12 \times 12}} = \dfrac{1}{2}$, so use these concept to reach the solution of the question.
Complete step-by-step answer:
Given data:
A job can be completed by 12 men in 12 days.
Now we have to find out how many extra days will be needed to complete the job, if 6 men leave after working for 6 days.
Let the work = 1
Now as the work is completed in 12 days by 12 men.
So the 1 day work of 12 men = $\dfrac{1}{{12}}$.
So the 1 day work of 1 man = $\dfrac{1}{{12 \times 12}}$
So the 6 day work of 1 man = $\dfrac{6}{{12 \times 12}}$.
So the 6 day work of 12 men = $\dfrac{{6 \times 12}}{{12 \times 12}} = \dfrac{1}{2}$.
So the remaining work after 6 days work of 6 men = total work – 6 day work of 12 men.
Therefore, the remaining work after 6 days work of 6 men = 1 – $\dfrac{1}{2}$ = $\dfrac{1}{2}$
So $\dfrac{1}{2}$ work is remaining.
Now after 6 days 6 workers go on leave, so the remaining work is done by the remaining 6 workers.
Let the number of days taken by remaining 6 workers be X.
So, the 12 men can complete 1 work in 12 days which is equal to 6 men can complete $\dfrac{1}{2}$work in X days.
Therefore, $\dfrac{1}{{12 \times 12}} = \dfrac{{\dfrac{1}{2}}}{{6 \times x}}$
Now simplify it we have,
$ \Rightarrow 6x = \dfrac{1}{2}\left( {144} \right)$
$ \Rightarrow x = \dfrac{{72}}{6} = 12$ days.
So the total number of days to finish the work this time = 12 + 6 = 18 days
So the number of extra days which is needed to complete the work = 18 – 12 = 6 days.
Hence option (c) is the correct answer.
Note: Whenever we face such types of questions the key concept we have to remember is that always recall that 12 men can complete 1 work in 12 days which is equal to the 6 men can complete $\dfrac{1}{2}$work in X days, so just covert this information into equation as above and simplify we will get the number of days in which the remaining work is finished, so the total work is finished is the sum of the previous days in which all 12 workers working and the number of days in which 6 workers are working so the extra number of days is the difference of current scenario days in which total work is finished into two parts and the number of days in which total work is finished in only one part.
Complete step-by-step answer:
Given data:
A job can be completed by 12 men in 12 days.
Now we have to find out how many extra days will be needed to complete the job, if 6 men leave after working for 6 days.
Let the work = 1
Now as the work is completed in 12 days by 12 men.
So the 1 day work of 12 men = $\dfrac{1}{{12}}$.
So the 1 day work of 1 man = $\dfrac{1}{{12 \times 12}}$
So the 6 day work of 1 man = $\dfrac{6}{{12 \times 12}}$.
So the 6 day work of 12 men = $\dfrac{{6 \times 12}}{{12 \times 12}} = \dfrac{1}{2}$.
So the remaining work after 6 days work of 6 men = total work – 6 day work of 12 men.
Therefore, the remaining work after 6 days work of 6 men = 1 – $\dfrac{1}{2}$ = $\dfrac{1}{2}$
So $\dfrac{1}{2}$ work is remaining.
Now after 6 days 6 workers go on leave, so the remaining work is done by the remaining 6 workers.
Let the number of days taken by remaining 6 workers be X.
So, the 12 men can complete 1 work in 12 days which is equal to 6 men can complete $\dfrac{1}{2}$work in X days.
Therefore, $\dfrac{1}{{12 \times 12}} = \dfrac{{\dfrac{1}{2}}}{{6 \times x}}$
Now simplify it we have,
$ \Rightarrow 6x = \dfrac{1}{2}\left( {144} \right)$
$ \Rightarrow x = \dfrac{{72}}{6} = 12$ days.
So the total number of days to finish the work this time = 12 + 6 = 18 days
So the number of extra days which is needed to complete the work = 18 – 12 = 6 days.
Hence option (c) is the correct answer.
Note: Whenever we face such types of questions the key concept we have to remember is that always recall that 12 men can complete 1 work in 12 days which is equal to the 6 men can complete $\dfrac{1}{2}$work in X days, so just covert this information into equation as above and simplify we will get the number of days in which the remaining work is finished, so the total work is finished is the sum of the previous days in which all 12 workers working and the number of days in which 6 workers are working so the extra number of days is the difference of current scenario days in which total work is finished into two parts and the number of days in which total work is finished in only one part.
Recently Updated Pages
10 Examples of Evaporation in Daily Life with Explanations
10 Examples of Diffusion in Everyday Life
1 g of dry green algae absorb 47 times 10 3 moles of class 11 chemistry CBSE
If the coordinates of the points A B and C be 443 23 class 10 maths JEE_Main
If the mean of the set of numbers x1x2xn is bar x then class 10 maths JEE_Main
What is the meaning of celestial class 10 social science CBSE
Trending doubts
Fill the blanks with the suitable prepositions 1 The class 9 english CBSE
Which are the Top 10 Largest Countries of the World?
How do you graph the function fx 4x class 9 maths CBSE
Differentiate between homogeneous and heterogeneous class 12 chemistry CBSE
Difference between Prokaryotic cell and Eukaryotic class 11 biology CBSE
Change the following sentences into negative and interrogative class 10 english CBSE
The Equation xxx + 2 is Satisfied when x is Equal to Class 10 Maths
In the tincture of iodine which is solute and solv class 11 chemistry CBSE
Why is there a time difference of about 5 hours between class 10 social science CBSE