Answer
Verified
461.1k+ views
Hint: Find the units of work done by each of them per day then we can find number of units of total work. Do this by using per day fraction of work.
\[Per\text{ }day\text{ }fraction\text{ }=\text{ }\dfrac{1}{Time\text{ }taken}\]
Complete step-by-step answer:
They will work together for 2 days and finish the work.
Case 1: Let the time taken by A to finish a piece of work be a. Then the per day fraction of work done by A will be $\left( \dfrac{1}{a} \right)$
Case 2: Let the time taken by B to finish a piece of work be b. Then the per day fraction of work done by B will be $\left( \dfrac{1}{b} \right)$
Case 3: Let the time taken by C to finish a piece of work be c. Then the per day fraction of work done by C will be $\left( \dfrac{1}{c} \right)$
So,
Total per day fraction of work will be sum of all cases
Total per day fraction of work = (Case 1) + (Case 2) + (Case 3)
Total per day fraction of work = $\dfrac{1}{a}+\dfrac{1}{b}+\dfrac{1}{c}$
We know:
(Total time).(Total per day fraction of work) = 1
Here 1 implies that work is completed.
So, by substituting 2 days into equation, we get:
$2\left( \dfrac{1}{a}+\dfrac{1}{b}+\dfrac{1}{c} \right)=1.........(i)$
Given:
A take twice as much time as B.
A take thrice as much time as C.
By using above conditions, we get:
a = 2b and a = 3c
By substituting these into equation(i), we get
$2\left( \dfrac{1}{a}+\dfrac{1}{\dfrac{a}{2}}+\dfrac{1}{\dfrac{a}{3}} \right)=1$
By solving this, we get:
$2\left( \dfrac{1}{a}+\dfrac{2}{a}+\dfrac{3}{a} \right)=1$
By taking least common multiple and then adding the fractions, we get:
$2\left( \dfrac{6}{a} \right)=1$
By multiplying both sides with a, we get:
$\dfrac{12}{a}.a=a$
a = 12
By using given conditions, we found relation between a and b:
a = 2b
By substituting value of a, we get:
12 = 2b
By dividing 2 on both sides, we get:
$b=\dfrac{12}{2}=6$
Therefore, it takes 6 days for B to complete the work alone.
Option (d) is correct.
Note: Do not confuse time taken and per day fraction of work. The simple relation is stated in the hint.
\[Per\text{ }day\text{ }fraction\text{ }=\text{ }\dfrac{1}{Time\text{ }taken}\]
Complete step-by-step answer:
They will work together for 2 days and finish the work.
Case 1: Let the time taken by A to finish a piece of work be a. Then the per day fraction of work done by A will be $\left( \dfrac{1}{a} \right)$
Case 2: Let the time taken by B to finish a piece of work be b. Then the per day fraction of work done by B will be $\left( \dfrac{1}{b} \right)$
Case 3: Let the time taken by C to finish a piece of work be c. Then the per day fraction of work done by C will be $\left( \dfrac{1}{c} \right)$
So,
Total per day fraction of work will be sum of all cases
Total per day fraction of work = (Case 1) + (Case 2) + (Case 3)
Total per day fraction of work = $\dfrac{1}{a}+\dfrac{1}{b}+\dfrac{1}{c}$
We know:
(Total time).(Total per day fraction of work) = 1
Here 1 implies that work is completed.
So, by substituting 2 days into equation, we get:
$2\left( \dfrac{1}{a}+\dfrac{1}{b}+\dfrac{1}{c} \right)=1.........(i)$
Given:
A take twice as much time as B.
A take thrice as much time as C.
By using above conditions, we get:
a = 2b and a = 3c
By substituting these into equation(i), we get
$2\left( \dfrac{1}{a}+\dfrac{1}{\dfrac{a}{2}}+\dfrac{1}{\dfrac{a}{3}} \right)=1$
By solving this, we get:
$2\left( \dfrac{1}{a}+\dfrac{2}{a}+\dfrac{3}{a} \right)=1$
By taking least common multiple and then adding the fractions, we get:
$2\left( \dfrac{6}{a} \right)=1$
By multiplying both sides with a, we get:
$\dfrac{12}{a}.a=a$
a = 12
By using given conditions, we found relation between a and b:
a = 2b
By substituting value of a, we get:
12 = 2b
By dividing 2 on both sides, we get:
$b=\dfrac{12}{2}=6$
Therefore, it takes 6 days for B to complete the work alone.
Option (d) is correct.
Note: Do not confuse time taken and per day fraction of work. The simple relation is stated in the hint.
Recently Updated Pages
How many sigma and pi bonds are present in HCequiv class 11 chemistry CBSE
Mark and label the given geoinformation on the outline class 11 social science CBSE
When people say No pun intended what does that mea class 8 english CBSE
Name the states which share their boundary with Indias class 9 social science CBSE
Give an account of the Northern Plains of India class 9 social science CBSE
Change the following sentences into negative and interrogative class 10 english CBSE
Trending doubts
Differentiate between homogeneous and heterogeneous class 12 chemistry CBSE
Difference between Prokaryotic cell and Eukaryotic class 11 biology CBSE
Difference Between Plant Cell and Animal Cell
Fill the blanks with the suitable prepositions 1 The class 9 english CBSE
Which are the Top 10 Largest Countries of the World?
Give 10 examples for herbs , shrubs , climbers , creepers
10 examples of evaporation in daily life with explanations
The Equation xxx + 2 is Satisfied when x is Equal to Class 10 Maths
Why is there a time difference of about 5 hours between class 10 social science CBSE