Courses
Courses for Kids
Free study material
Offline Centres
More
Store Icon
Store
seo-qna
SearchIcon
banner

A, B and C can reap a field in 1534 days; B, C and D in 14 days; C, D and A in 18 days; D, A and B in 21 days. In what time can A, B, C and D together reap it?

Answer
VerifiedVerified
459k+ views
like imagedislike image
Hint: We first have to express the given equation as an equation with terms A, B, C and D.
We have to write the work done by A, B, C, and D with the given conditions by taking the reciprocal of the time taken. We then have to convert 1534 into a fraction. Therefore, the work done by them can be found by adding all the obtained equations. Add the RHS taking the LCM. Divide the whole equation by 3 and cancel out 3 from the numerator and denominator of the LHS. We get the value of A+B+C+D which is the work done by them. We need to take the reciprocal of work done to get the time taken by A, B, C, and D to reap the field.

Complete step by step solution:
According to the question, we are asked to find the total number of days it takes to reap together by A, B, C and D.
We have been given that A, B and C can reap a field in 1534 days.
Let us convert the statement into an equation, we get
Time taken by A, B and C to do the work are 1534 days.
We need to convert 1534 into a fraction for further calculation.
To convert a whole number abc into a fraction, we use the formula abc=ac+bc.
Here a=15, b=3 and c=4.
Therefore, 1534=15×4+34
1534=60+34
Hence, we get 1534=634.
Time taken to complete the work by A, B and C is 634 days.
Therefore, the work done by A, B and C in one day is the reciprocal of the number of days.
Let us convert the statement into an equation, we get
A+B+C=463 ---------------(1)
Also, we know that the time taken by B, C and D to reap is 14 days.
Therefore, the work done by B, C and D is
B+C+D=114 ---------------(2)
Then, we have been given that the time taken by C, D and A to reap is 18 days.
Therefore, the work done by C, D and A is
C+D+A=118 ---------------(3)
Similarly, we know that the time taken by D, A and B to reap is 21 days.
Therefore, the work done by D, A and B is
  D+A+B=121 ---------------(4)
Let us now add all the four equations (1), (2), (3) and (4).
We get the work done is
A+B+C+B+C+D+C+D+A+D+A+B=463+114+118+121
Let us now group all the similar terms.
(A+A+A)+(B+B+B)+(C+C+C)+(D+D+D)=463+114+118+121
On further simplifications, we get
3A+3B+3C+3D=463+114+118+121
We find that 3 are common in the LHS of the equation. On taking 3 common from the equation, we get
3(A+B+C+D)=463+114+118+121 ---------------(5)
Now, we have to solve the RHS of equation (5).
Let us take the LCM OF 63, 14, 18 and 21.
3|63,14,18,21
3|21,14,6,7
2|7,14,2,7
7|7,7,1,7
1|1,1,1,1
Therefore, LCM= 3×3×2×7
LCM=126.
In equation (5), we get
3(A+B+C+D)=4×2+9+7+6126
3(A+B+C+D)=8+9+7+6126
3(A+B+C+D)=30126
We can write the above equation as
3(A+B+C+D)=3×103×42
Since 3 are common in both the numerator and denominator of RHS, we can cancel 3.
3(A+B+C+D)=1042
Now, on further simplification, we get
3(A+B+C+D)=2×52×21
Since 2 are common in both the numerator and denominator of RHS, we can cancel 2.
3(A+B+C+D)=521
Now, let us divide the whole equation by 3. We get
3(A+B+C+D)3=521×3
3(A+B+C+D)3=563
We find that 3 are common in both the numerator and denominator of the LHS.
Let us cancel 3, we get
A+B+C+D=563
Therefore, the work done by A, B, C and D is 563.
The time taken by A, B, C and D is 1563=635.

Hence, the time taken by A, B, C and D together reap the field is 635 days.

Note: We can further simplify the obtained answer by converting it into a mixed fraction.
We have to divide 63 by 5, that is the divisor is 5 and the dividend is 63.
5)6351310312
Here, the quotient is 12 and the remainder is 3.
We have to write the mixed fraction as quotientremainderdivisor.
Therefore, 635=1235.
Hence, the time taken by A, B, C and D together to reap the field is 1235 days.